[ARCHIVED] Water Construction Update Week of May 30th, 2022

Two crews will be working in the following areas:
 
1. Dig It will begin water main and hydrant installation on Spring Tide Lane, Mean Tide Court, High Tide Place

2. Lynch will begin final paving on Jackcin Drive, Linda Lane, Apple Way, Orchard Way, Seashell Lane, Preservation Way (weather permitting) 


Dig It’s working hours are 7:00 a.m. to 5:00 p.m. Monday – Thursday. No paving will occur on Monday in observance of Memorial Day.


Access and egress will be maintained. There will be signage and detail officers to direct traffic during construction. Please use caution when approaching and passing construction crews.
 
Questions or concerns about construction? Email Environmental Partners, the Town’s engineer, at easthamwater@envpartners.com or leave us a voicemail at 617-657-0279. Questions can also be directed to Kim St. Aubin at waterclerk@eastham-ma.gov or 774-801-3244.